Work packages

Work package 1: Inventory of user groups, usage and user environment
Duration: Month 0 - 6
Workpackage leader: Radboud Revalidatie

Work package 2: Functional analysis and specifications
Duration: Months 0 - 12
Workpackage leader: Zuyd University

Work package 3: Development of concepts and decision making on final concept
Duration: Months 5 - 17
Workpackage leader: M2C

Work package 4: Designing and prototype building
Duration: Months 5 – 24.
Workpackage leader: Focal Meditech

Work package 5: Field evaluations, final improvements and documentation
Duration: Months 13 – 36
Workpackage leader: MUMC+

Work package 6: Dissemination, publications and finalisation
Duration: Months 0 - 36
Workpackage leader: TU-E